 - Go into Objects and Containment
 
  - Create two new objects:
  
  
- Check Display Object Value
- Select Define Object Dimensions and 3D Control
  
   - Change the color of each new object
 
 
- Next go into Resources and Shifts
 
  - Create two new Resources and set Available Number:
  
   - 'Resource1' - 1
- 'Resource2' - 1
- Be sure to click Add after each entry
 
 
- Use the Start Process tool to create 'Start
- Use the Generic Process tool to create: 'Process1' and 'Process2'
- Lastly use an End Process tool and create 'End'
- Now use the Interprocess Connection tool and connect the model together
 
  - 'Start' to both 'Process1' and 'Process2'
- Connect both of those to 'End'
 
- Select 'Start'
 
  - Go into Define Object Creation Rules
  
   - Switch to Create Objects Based on Distribution and set the Distribution for each object:
   
    - 'Part1' - 50
- 'Part2' - 50
 
 
- Customize and switch to Process/Object/Condition Routing
  
   - Set the Default Routing to 'Process1'
- Set 'Part2' to 'Process2'
 
 
- Now select 'Process1'
 
  - Go into Process Timing Properties
  
   - Set Default Timing to a Min/Max of 5 Seconds
 
- Customize and go into Resource Constraints
  
   - Set the Required Number for 'Resource1' to 1
 
- Select the connection lines before and after 'Process2', right click and select Item Properties
  
   - Customize and go into Resource Constraints
   
    - Set the Required Number for 'Resource2' to 1
 
 
- Switch to the Simulation tab
  
  
- As the model runs watch as the Resources work differently for each object.